This article covers everything you need to know about European Double Girder Overhead Crane Installation, including three sections: pre-installation preparation, installation steps, and post-installation testing. Whether it’s your first time installing a European double girder bridge crane or you’ve done it several times before, we hope you’ll learn something to ensure that your next project goes as planned, stays within budget, and keeps your workers safe.
1. In the quotation, the crane installation team will specify the time frame they expect to complete the installation. These times need to be cleared in advance. Once the crane and all other installation equipment are brought to the site, they cannot interrupt or stop and restart the installation process without significantly increasing the cost.
2. Upon receiving the purchase order, the bridge crane manufacturer will begin building the crane. The installers need to establish contact with the necessary parties about a month before the estimated completion date to schedule a visit to evaluate the worksite or facility and agree on the installation schedule.
3. Evaluate the scope of work
4. Identify potential hazards
The overhead crane installation team must identify any potential hazards to plan and prepare their team accordingly. To ensure the crane installation is completed correctly, different hazards may require specialized protection for their team (PPE), special permits, and other considerations. Before installing the bridge crane, the installers will look for the following categories of hazards:
1. Use a crane to lift the end beam. Align the positioning sleeve of the end beam with the positioning hole of the main beam, then connect them with a bolt set. Finally, use a wrench to tighten the bolts securely.
2. Mark the bolts with an anti-loosening mark.
3. Install the rain cover on the handhole of the end beam.
4. After using a crane to align the connecting beam with the end beam, install the end beam fixing shaft, then attach a stopper plate to the end of the fixing shaft.
5. Install the hook stopper. Once the hook stopper is aligned with the connecting beam, connect and secure it using a bolt set.
6. Install the load capacity sign on the railing of the gantry walkway. Secure the anti-detachment chain of the load capacity sign to the sign itself using a bolt set.
1. Install the crane buffer extension rod and buffer on the end beam on the walkway side, and install the crane buffer on the opposite side. Connect and secure them with a bolt set.
2. Install the crane photoelectric limit switches at both ends of the end beam on the conductor line side. First, install the limit switch bracket on the end beam, then mount the limit switch onto the bracket.
1. Use a crane to lift the trolley and install it onto the main beam’s track.
2. Install the trolley conductive bracket and secure it with a bolt set.
3. Install the trolley cross limit switch (slightly higher than the limit trigger rod) and secure it with a bolt set.
4. Position the trolley limit trigger rod according to the drawings, install it, and secure it with a bolt set.
5. Install the trolley terminal box aviation plug.
1. Install the electrical cabinet and resistor on the main beam walkway. Use a crane to lift the electrical cabinet to a certain height above the electrical cabinet base. Connect the aviation plug from the bottom of the electrical cabinet, then securely fasten the electrical cabinet with a bolt set. Use a crane to lift the resistor onto the resistor base and secure it with a bolt set.
2. Connect the wiring for the crane travel motor, and after completing the wiring, secure the junction box cover with screws.
3. Install the crane lighting fixture onto the lamp bracket and secure it with a bolt set.
After completing the complex installation process, it’s time for load testing. This crucial step ensures that all components are functioning properly. Manufacturers typically hire a third-party testing company to ensure impartiality.
Before the first use, your new crane system must pass two operational tests and one rated load test to comply with OSHA 1910.179 regulations for bridge and gantry cranes:
Always keep records of the load tests for future reference.
Kuangshan Crane is a specialist in manufacturing and installation services. We provide professional installation masters and detailed installation guidance.
What is the overhead crane installation cost?
Please note that this option requires your factory or team to have professional installation personnel and the necessary lifting equipment for installing the bridge crane. We will provide you with detailed installation documents, videos, and other reference materials free of charge.
We offer on-site engineer deployment services to provide installation guidance. You will need to provide the necessary equipment and installation workers. Additional costs associated with this service include visa fees for the engineer, round-trip airfare, meals, accommodation, personal safety, and a daily wage of $200 per person.